1886 Solar Energy Station Interconnection Project
This website provides information on the development of the 1886 Solar Energy Station 500-kV Interconnection Project in Coconino County, Arizona.
Project Overview
1886 Solar Energy Station LLC, a wholly owned subsidiary of Stellar Renewable Power (Stellar), plans to develop the 1886 Solar Energy Station Interconnection Project (Interconnection Project) in Coconino County, Arizona. The Project involves a new, approximately 5-mile-long, 500-kV generation intertie (gen-tie) transmission line that parallels the existing 500-kV Moenkopi to Cedar Mountain Transmission Line. The Interconnection Project would connect Stellar's planned 1886 Solar Energy Station to the regional electric grid at a planned Arizona Public Service (APS) switchyard. The Interconnection Project will have a 250-foot right-of-way. The 1886 Solar Energy Center involves solar/photovoltaic generating facility and battery energy storage system, each with a capacity of up to 500 megawatts (MW). The Interconnection Project would be approximately 30 miles northwest of Flagstaff; the proposed route is shown on the map below.
In June 2022, Coconino County approved conditional use permits (CUP) for a project referred to as CO Bar Solar. In August 2022 Stellar acquired a portion of CO Bar Solar from the original developer; the portion Stellar acquired is referred to as the 1886 Solar Energy Station. The relevant CUP approvals were transferred to Stellar. Prior to starting construction, the Interconnection Project will require other major environmental approvals including a Certificate of Environmental Compatibility (CEC) from the Arizona Corporation Commission and an environmental assessment (EA) from the U.S. Bureau of Reclamation (USBOR). Arizona state law requires a CEC for new transmission lines that operate at 115 kV or above and are longer than one mile. The USBOR is a part owner of the Moenkopi to Cedar Mountain 500kV transmission line, the point of interconnection for the Project. The USBOR must complete an environmental review of the proposed interconnection in compliance with the National Environmental Policy Act of 1969 (NEPA) prior to approving the Project's interconnection request. Stellar expects USBOR to prepare an environmental assessment for the Project to assess the environmental effects of the proposed interconnection. Stellar aims to start construction on the 1886 Solar Energy Center in Q3 2024.
By connecting the PV solar array and BESS to the regional electric grid, the Project will help APS meet its peak electrical load requirements and, in so doing, will lessen the need to dispatch less efficient, non-renewable "peaking resources." By including an energy storage facility, the Project will facilitate the further integration of intermittent generating resources (e.g., solar and wind energy).
Public Comment
Stellar hosted an in-person neighborhood open house on June 20, 2023, to provide the public an opportunity to learn more about the Interconnection Project. Stellar continues to welcome public and stakeholder input. Comments and questions may be submitted through this website (scroll below) or through the following points of contact:
Project telephone line: (928) 288-2634
Project email: 1886solar@swca.com
Project mailing address: 1886 Solar Energy Station Interconnection Project
c/o SWCA Environmental Consultants
1645 South Plaza Way
Flagstaff, Arizona 86001
About Stellar
Stellar is a renewable energy company headquartered in Dallas, Texas. Stellar has experience at every stage of developing renewable energy projects (e.g., planning, designing, permitting, constructing, and operations). Stellar's vision is to build a world-leading renewable development portfolio to accelerate the transition to a carbon free future. Stellar has a project development pipeline with over 4.5 gigawatts (GW) across the U.S.
Certificate of Environmental Compatibility Process
A Certificate of Environmental Compatibility (CEC) from the Arizona Corporation Commission and Arizona Power Plant and Transmission Line Siting Committee is required to allow for construction and operation of the 1886 Solar Energy Station Interconnection Project. Stellar filed its CEC application with the Arizona Corporation Commission (ACC) on July 24, 2023. The docket number for the Interconnection Project's CEC application is L-21260A-23-0218-00224. The CEC application includes environmental studies evaluating the proposed Interconnection Project.
The Arizona Power Plant and Transmission Line Siting Committee (Line Siting Committee) held a public hearing and public comment session for the Interconnection Project on September 7 and 8, 2023, in Flagstaff, Arizona. Transcripts from the public hearing are available below in the “Key CEC Documents” section.
During the public hearing, the Line Siting Committee voted to approve a CEC for the Interconnection Project. On October 26, 2023, the Arizona Corporation Commission issued its final approval for the CEC. A copy of the final approved CEC is available below in the “Key CEC Documents” section.
Key CEC Documents
CEC application, split into three files:
CEC Hearing Dates
EVENT | DATES |
---|---|
CEC hearings before the Arizona Power Plant and Transmission Line Siting Committee | 9/7, starting at 10:00 AM 9/8, starting at 9:00 AM (High County Conference Center, 307 West Dupont Ave., Flagstaff, Arizona 86001) |
Public comment session | 9/7, starting at 5:30 PM (High County Conference Center, 307 West Dupont Ave., Flagstaff, Arizona 86001) |
Public comment Vimeo | 9/7, starting at 5:30 PM |